Name: MATERA SOLAR PLANT
Project details: 2MWp Ground mounted system
The park, built in the town of Matera, in the Basilicata County during the 2011 using a ground mounted system, delivers a power of 2MWp.
Renergy Power Plants was commissioned of the full preconstruction development and full design package prior to project management, delivering the complete construction, civil, mechanical and electrical, of the park, managing the materials supply and the logistic of the site.
Ending the work with the commissioning of the park.
SCOPE OF WORK:
- Full design package;
- Execution planning;
- Project management;
- Construction
- Commissioning.
-
2011
-
Engineering
-
Construction
-
Matera, Basilicata, Italy